SEPTEMBER SCHOOL CONSTRUCTION NEWSLETTER!!

Posted Date: 10/03/25 (11:39 AM)

TC

CONSTRUCTION UPDATE

CRESCENT HARBOR ELEMENTARY I SEPTEMBER 2025

 
Looking at the building from the outside, we can all clearly see the progress. Brickwork is nearing completion, and windows continue to be fitted.

In the interior of the building, lots of exciting projects are shaping the new school. From wallpaper and paint, cabinets and kitchen appliances, to skylights and mechanical equipment. September brought it all.

Here's what it looks like on site:
 
1
This image is from September 3rd. The outside façade is mostly finished, with a few areas still awaiting brick coverage.
 
2
The back of the building. The complementary brickwork is complete.
 
3
4
The main corridors feature curved architecture, guiding students to various areas of the building.
 
5
6
Corridors and classrooms are beginning to take shape with paint and wallpaper. Currently, we have two corridors painted with orange accents and two corridors painted green.
 
7
Heating units in each classroom will be cleverly hidden underneath cabinets. In this image, you can see the heating across 2 walls. Classrooms also feature ceiling fans.
 
9
The window surround shows the colors that are being used throughout the new building.
 
10
Looking down into the inner courtyard.
 
11
Taken on September 12. The entrance to the new school.
 
12
Cabinets for classrooms were delivered on September 15th.
 
12
Cabinet installation.
 
13
Students' cubbies and storage area. The same cabinets are featured in all teacher classrooms.
 
14
Counter tops and sinks for the classrooms will be fitted during October.
 
16
New mechanical equipment delivered to the pump house on September 19th.
 
20
The image was taken on September 29th, and the brickwork on the front of the building is pretty much complete.
 
21
The new CHE kitchen features new shiny equipment.
 
22
The new kindergarten classrooms all have a bathroom.
 
23
Plenty of natural light in the new library. The library is situated on the 2nd floor at the front of the building.
 
23
The ceiling of the commons area was painted on September 29th. You can view this area from a window in the library.
 
25